General Information Board of Education Policies and Regulations Superintendent of Schools Inside Your Schools Parent Newsletter Instructional Calendar Curriculum Standards Summer Programs BTSA Infinite Campus Assessment, Research and Evaluation Contact Us Staff Resources
School Site Locator / Attendance Boundary Maps Elementary Schools Middle Schools High Schools Feeder Schools Alternative Education Parent Portal/School Registration Safe School Efforts Open House Dates 2014 Back-to-School-Night Dates Graduation Dates Enrollment School Accountability Report Cards (SARC) Comprehensive School Safety Plan (CSSP) Single Plan for School Achievement (SPSA) DataQuest Reports
Work Permit Pertussis information
Parent Portal Enroll Your Child 2014-2015 School Site Specific Registration Information Have You Moved? School Transfers Every School Day Counts Child Care School Lunches Volunteer Requirements Annual Parent Information Packet Parents' Rights Section 504 GATE English Learner Support Services Parent Resources Special Needs Ombuds SRV Council of PTAs Classes for Parents English Learner Support Services Forms LCAP/LCFF
Facility Use/Rental District Flyer Approval and Distribution San Ramon Valley Education Foundation Student Recognition Project CBS5 story - Great Schools
Business Services Child Nutrition Communications & Community Relations Educational Services Duplicating Facilities Human Resources Maintenance and Operations Purchasing Special Education Student Services Superintendent's Office Technology Transportation Warehouse Special Needs Ombuds
Human Resources Benefits Certificated Classified Fingerprinting Forms Job Descriptions/Salary Schedules Substitute Web Based System

Contact Information

RIchard Lowell
Director of Facilities
(925) 552-2970

San Ramon Valley USD
Facilities Development

3280 Crow Canyon Rd.
San Ramon, CA 94583

Solar Overview

SRVUSD is proud of its initiative to construct and operate solar arrays in the parking lots of five schools in the District: California High School (CHS), Dougherty Valley High School (DVHS), Monte Vista High School (MVHS), San Ramon Valley High School (SRVHS), and Diablo Vista Middle School (DVMS). These five systems are comprised of more than 10,000 panels. The systems, by contract, began converting solar energy to electricity at these schools starting October 1, 2011.  Gale Ranch Middle School (GRMS) was added in 2012.

CHS 2014 CHS 2014 CHS Solar Installation Progress Photos August 2011 DVHS Solar Installation Progress Photos August 2011 DVHS Solar Installation Progress Photos August 2011 DVMS Solar Installation Progress Photos August 2011 Diablo Vista Middle School Monte Vista High School Monte Vista High School SRVHS Solar Installation Progress Photos August 2011 SRVHS SunPower aerial 111511
Status area

Overview

  • First 5 schools completed in 2011
  • First Year Expected Output:  6.2 million kWh/year overall at 5 schools:
    • CHS, DVHS, MVHS, SRVH, DVMS
  • Gale Ranch was added in 2012 (fixed tilt)
  • Over 10,000 panels district-wide.  SunPower panels are the most efficient in the world at converting solar energy to electricity
  • System data by site:

School

System Rating

(kW DC)

Expected 1st Year Output

(kWh)

California HS

750

1,365,642

Dougherty Valley HS

1,023

1,873,050

Monte Vista HS

886

1,623,032

San Ramon Valley HS

497

841,537

Diablo Valley MS

259

475,922

Subtotal first 5 sites:

3,415

6,179,183

Gale Ranch MS

274

434,146

Total:

3,689

6,613,329

 

  • System will generate over 2/3 of the electricity required to run these five schools
     
  • The project is funded by $25,000,000 in low interest QSCBs.  The SunPower contract for design and construction of a 3.4 mW system is $23,277,682.  Balance of funding may be used for inspection, security, bond costs, technical consultants, contingency for hidden conditions, and other soft costs.  In 2012 Gale Ranch was added for $1,499,135.
     
  • Base prices without maintenance or performance guarantee:
    • First 5:  $22,725,261 ($6.65 per kWp)
    • Gale Ranch:  1,379,452 ($5.03 per kWp)
       
  • 17 year output guaranteed by SunPower at 95% of expected performance
    • If actual performance is less than the adjusted expected performance, SunPower will pay the district for lost savings based on historical rates – as well as lost utility rebates.
       
  • Warranties
    • Solar panels have 25 year warranties
    • Inverters have 20 year warranties
       
  • Maintenance agreement for 17 years included in price
     
  • The height of the support structures range from 12 feet to 18 feet high, with the tracker systems mounted on top.  Gale Ranch is fixed tilt
     
  • The project has been reviewed and approved by the Division of State Architect as well as the local and State Fire Marshals.  Notification requirements under the California Environmental Quality Act (CEQA) have been met.

Performance Monitoring

Solar cumulative data monitoring: click here!

solar sun.jpg

FAQs related to district's solar initiative

Q: What is the San Ramon Valley Unified School District’s current Solar Project?

A: SRVUSD is in the final stages of constructing solar arrays in the parking lots of five schools in the District: ...more